Project Overview

The City of Ottawa completed a traffic calming study along Tapiola Crescent in response to long‑standing traffic and safety concerns raised by residents. The purpose of the study was to identify and recommend permanent roadway modifications aimed at reducing vehicle speeds and improving safety for all road users.


Current Status

Phase: Early Study and Concept Design

Progress Update:
City staff are currently completing the Project Charter, gathering survey data, and retaining a design consultant to advance the detailed design phase. A conceptual traffic calming plan has already been drafted based on preliminary findings.

Proposed Modifications Include:

Pedestrian Crossovers (PXOs) with Bulb‑Outs

Three new PXOs, each with curb narrowings to reduce crossing distances, are proposed at:

  1. Between Johnston Road West and Gentle Gate Crescent
  2. Between White Clover Private and Rastila Crescent / Tammela Court
  3. Between Brando Crescent / Rushford Private and Haxby Private

Concrete Center Medians

Two raised medians are proposed to narrow vehicle lanes and calm traffic:

  • Between Fireside Crescent and Crimson Gate
  • Between Rastila Crescent / Wingale Private and Brando Crescent / Somero Private

Note: Due to roadway width limitations, sections of on‑street parking near these medians would need to be removed.

Intersection Improvements

Tapiola Crescent & Johnston Road (East)

  • New crosswalk markings on the east leg
  • Upgraded pedestrian landing pads to meet current accessibility standards

Tapiola Crescent & Johnston Road (West)

  • Upgraded pedestrian landing pads to current accessibility standards

Timeline

  • Design and Tender: In progress, tender preparation starting April 2026
  • Construction timeline: Anticipated to start June 2026 following tender.

What’s Next

Upcoming Actions:

  • Design and construction tender May 2026
  • Notices to be sent to impacted residents April/May 2026
  • Construction set to start June 2026 following advance notice to residents.

Questions or Comments

Learn more here: Tapiola NTC

Project Lead:

Stacey Hogan, CET, CAPM
Project Manager | Gestionnaire de projet
City of Ottawa | Infrastructure Services | Design & Construction – Municipal
Email | Courriel: Stacey.Hogan@ottawa.ca