Project Overview

This multi-segment road rehabilitation project includes resurfacing along three major arterial corridors within Ward 10: Bank Street, Hunt Club Road, and Johnston Road. Work involves full pavement milling and resurfacing, as well as adjustments to catch basins and manholes. This preventative maintenance program extends the lifespan of critical roadway infrastructure and reduces long-term repair costs for these heavily travelled corridors.


Current Status

Phase: Completed Fall 2025

Construction Schedule:

  • Bank Street:
    July 15 – September 15, 2025 – Completed
  • Hunt Club Road:
    July 15 – August 29, 2025  – Completed
  • Johnston Road:
    August 11 – September 5, 2025 – Completed

What’s Next

Upcoming Actions:
No further work planned; resurfacing activities concluded in Fall 2025.

Community Involvement:
Residents were advised to relocate irrigation lines or garden beds near the roadway before work began. EV owners were encouraged to plan alternative charging options in cases where overnight driveway access was temporarily affected.