Location: 330 River Road
Project Type: Park Infrastructure – Boat Launch Replacement
Developer/Lead Agency: City of Ottawa (Parks, Recreation and Cultural Services)
Project Overview
Replacement of the existing boat launch at Eccolands Park featuring a new ramp constructed using a combination of pre-cast and cast-in-place reinforced concrete. The project aims to provide improved waterfront access and enhanced recreational boating facilities for the community. 100% design drawings have been completed by the consulting team.
Current Status
Phase: Permit Application Stage
Progress Update: Permit applications are currently in progress with multiple regulatory agencies including Transport Canada, Parks Canada, Fisheries and Oceans Canada, and the Rideau Valley Conservation Authority (RVCA). Transport Canada and Parks Canada permits are anticipated to require 4-6 months processing time.
Timeline: Construction anticipated for 2026, dependent on permit approvals
What’s Next
Upcoming Actions:
- Awaiting permit approvals from regulatory agencies, followed by tender process once permits and construction timing recommendations are received
Community Involvement: Construction timing updates will be provided as permit approvals are obtained and project schedule is confirmed