Conroy Rd and Davidson Roundabout

Mar 12, 2026 | News Updates

 

Location: Conroy Road at Davidson Road (offset intersection realignment)

Project Type: Transportation Infrastructure – Roundabout Intersection Realignment

Developer/Lead Agency: City of Ottawa – Infrastructure and Water Services Department (With design support from Novatech)


Project Overview

The City of Ottawa is undertaking the realignment and redesign of the Conroy Road / Davidson Road offset intersections to create a single, aligned intersection. The preferred option identified through preliminary design is a modern roundabout.

The project involves:

  • Realignment of the east leg of Davidson Road to line up with the west leg, requiring property acquisition from the National Capital Commission (NCC) and a land exchange agreement.
  • Construction of a new roundabout at the realigned intersection.
  • 500 m of roadway improvements on Davidson Road and 350 m on Conroy Road.
  • Multi-use pathway (MUP) installation around the roundabout.
  • Pedestrian crossovers (PXOs) on every leg of the roundabout.
  • Street lighting upgrades across the entire project area.
  • Roadside ditch modifications, reinstated or replaced culverts, and localized storm sewer installations to maintain proper drainage.
  • Speed limit reduction to 60 km/h approaching the new roundabout on both Conroy Road and Davidson Road.
  • Relocation of Hydro Ottawa infrastructure into the new Davidson Road right‑of‑way.
  • Naturalization of the existing east leg of Davidson Road once traffic is shifted to the new alignment.

Current Status

Phase: Preliminary Design Circulation

Progress Update:
Preliminary design drawings have been circulated internally for review. Property acquisition discussions with the NCC are underway.


Timeline

  • Environmental Assessment: Not required (localized road realignment)
  • Preliminary & Detailed Design: Ongoing through 2026
  • Construction Start: Fall 2026 (pending funding approval)
    • Clearing & grubbing in new Davidson Road right‑of‑way
    • Utility relocations continuing into late Fall 2026 and Winter 2027
  • Roadwork & Roundabout Construction: Spring–Fall 2027
  • Construction Completion: End of 2027

Project Budget

  • Approved funding to date: Not specified for this phase
  • Additional Council-approved funding required prior to commencing full road reconstruction in Fall 2026.
  • Final budget to be confirmed during detailed design.

What’s Next

Upcoming Actions:

  • Finalization of detailed design
  • Land exchange agreement with NCC
  • Utility relocation planning (Hydro Ottawa and others)
  • Preparation for clearing and grubbing in Fall 2026

Community Involvement:

A virtual public information session was held on April 10, 2025, to present the functional design options for a traffic control signal and a roundabout to the public. At this time attendees were able to review the design, ask questions and provide comment on the design options.

A second public information session is expected to be held in late fall 2025 to present the detailed design drawings to the public. At this time attendees will be able to review the design, ask questions and provide comment on the proposed works.

Updates will be shared as the project progresses toward construction.